[dpdk-dev] DPDK Release Status Meeting 24/01/2018
Mcnamara, John
john.mcnamara at intel.com
Fri Jan 25 10:24:33 CET 2019
Release Status Meeting 24/01/2018
28 June 2018
09:32
Agenda
------
* Subtrees
* Bugzilla
* Dates
Subtrees
--------
* Next-Net
* There are no critical/blocking issues. There is only a bunch of
patches merged, again nothing critical. Pulled from sub-trees.
It can be ready for Friday for rc4.
* Next-Crypto
* No patches
* Next-virtio
* Have prepared branch with 4 patches.
* Next-Eventdev
* No patches
* Next-Ip-pipeline
* No patches
* Master
* Documentation patches
RC4 target for Friday 25 January.
RC3 Testing
-----------
* No critical or very big issues for RC3 - from Intel Testing
LTS Testing
-----------
* Intel cannot test the LTS until after Chinese Spring Festival
* Should be able to start retesting in the week of Feb 18th
* Questions from Intel Test about the use of the Stable Tree.
Do people use it? Each stable/LTS release requires a lot of
testing and there are currently 3 releases to be tested.
Deprecation notices
-------------------
Please review the deprecation notices below:
* doc: add deprecation notice for meson: http://patches.dpdk.org/patch/49877/
* doc: add deprecation notice to remove rte meter color: http://patches.dpdk.org/patch/48712/
* doc: update API deprecation for device reset: http://patches.dpdk.org/patch/44990/
* doc: announce change of rte service API parameter type: http://patches.dpdk.org/patch/49987/
* doc: announce ring API change: http://patches.dpdk.org/patch/49961/
OVS 2.11 Status
---------------
* 2.11 branched from master January 18th.
* 4 week stabilization period.
* Release targeted February 18th~.
DPDK 19.05
----------
* Request for to try get some changes in early
* Agreement to accept proposed dates for 19.05
* Intel to submit patch to website to update dates
* Proposal Deadline: Friday 1 March 2019
* Merge deadline: Friday 22 March 2019
* RC1 release: Friday 29 March 2019
* Release: Friday 10 May 2019